New builds Progress
9 weeks and our 2 new builds in London are ready for the roof to go on straight after Xmas.
Groundwork – Mains drainage – 1st floor steel frame and floor then all brickwork and 6 roof steels complete in the 9 weeks. It’s great progress for a challenging site and a full job report including pictures will be added to our FMB.